          After being interrupted by a particularly brutal winter, work has resumed on several projects at Westside Park.

          City Manager, Amy Leon, talks about the flurry of activity…

          GeoTek is on site and conducting permeability testing for the pond, which may take up to 3 weeks. Additional clay and landscape rock around the island will begin on May 3rd and is expected to take 2 weeks.

          The McVay and Labyrinth Project should have the sidewalk completed this week; with landscaping, lighting and seeding to follow the week of May 15th. Final masonry and paver work should happen in early June, with the completion by June 29th.